Today we began our regular drilling schedule. In an attempt to limit our water use in the upper, dry portion of the hole, we are using foam as a lubricant. It will take some time to determine the proper foam/water mix for the drilling conditions, but so far the foam is doing its job well.
By the end of the day shift, drilling had progressed to a depth of 60 ft. At 100 ft we will stop and widen the hole with a rotary bit, then set and cement casing to that depth. This casing will help prevent the loose rock near the surface from caving into the drillhole.